·       Airglades Airport Drainage Improvements

 

The Airglades Airport Drainage Improvements is contracted with Gulf Paving in the amount of $2,675.000.00

 

·       Sidewalks at Cowboy Way  

 

The sidewalk is being constructed by the Road & Bridge Department. The sidewalk runs from Pratt Blvd to Collingswood Parkway.

 

·        CR 833 from  Dooley Grade to 2.75 miles South of Keri Rd.

   

Widening and Resurfacing  FM#422363-1-5801.  Awarded to AJAX Paving in the amount of $593,521.36 for Alternate B.  100% funded by FDOT.

 

·        CR 833 from 4 miles North of Big Cypress Indian Reservation to Margarita Curve

 Widening and Resurfacing FM# 422364-1-5801.  Awarded to AJAX Paving in the amount of $859,007.16.  100% funded by FDOT.


·       Master Pedestrian Pathway Plan

 

The Master Pedestrian Pathway Plan was awarded to Kimley-Horn and they are in the process of going to community meetings to get the public input. 


·       Felda MSBU Drainage Plan

 

The Felda MSBU Drainage Plan has been awarded to Tetra Tech in the amount of $259,000.  This project is funded $200,000 through a DEP grant

and $59,000 from the Felda MSBU Special District’s budget. 

·       Construction of Sidewalk Improvements on SR 29 FM # 426024-1-58-01

The project was awarded to Cougar Construction in the amount of $314,737.75.  The project is 100% funded from FDOT through Federal Stimulus funds.